The
Project Moves On
After
a lot of hard work and battling the elements, the project moved on
with Phase I being completed. There were a few problems encountered
along the way. The first surprise was that the existing drain pipe
coming from the shaft was not actually connected! The original idea
of connecting directly to the pipe had to be scraped leaving Grguric
Excavation no choice but to dig out the existing pipe and around the
shaft. Just when things were coming back together, the existing flow
valve was corroded and unusable. This forced the contractor to build
a new valve to be used in the project. To make a long story short, A
new pipe connected to the shaft and many leaks around the shaft were
sealed. Once this work was done, the discharge was directed across
the dam where the new flow valve was installed.
After the work around the shaft was
completed, the pipe for taking the discharge down to the treatment
area arrived. As it turned out, the truck drive was from Oklahoma
and was astonished that he was able to get his truck to the site.
Once the pipe was unloaded, it was time to start digging the trench.
Within a week, the pipe was laid and buried, and the entire site was
heavily seeded and mulched. This completed Phase I of the project.
Phase II will include clearing and grubbing of the treatment area,
excavation of the ponds, and redirecting the discharge to the
treatment area. Stay tuned!
Follow
the photos below to see the progress of the project. Simply select
each photo for a bigger view!
|
|
|
|
The path is cleared
to pipe the discharge
|
Treatment area is
brushed
|
Manhole sits waiting
to be placed
|
|
|
|
Art Grguric points to
the discharge valve
|
Steel pipe for taking
discharge over pond
|
Pipe arrives from
Oklahoma
|
|
|
|
Unloading the large
load of pipe
|
Area around shaft
had to be cleared
|
View down the
dugout shaft pipe
|
|
|
|
View of the modified
shaft and pipe
|
Overall view of piped
discharge and shaft
|
Flow control valve is
placed in the manhole
|
|
|
|
Art Grguric inspects
the installed pipe
|
Large amounts of
iron on the dam
|
Art Grguric is happy
with the progress
|